www. PMP - Certification - Exam .com
 
 
 

PMP Acronyms

 
According to PMI, project management best practices are accompanied by a vocabulary. This project management vocabulary contains acronyms that are most commonly understood and used throughout project management activities.
 
Acronym Definition
AC Actual Cost
ACWP Actual Cost of Work Performed
AD Activity Description
ADM Arrow Diagramming Method
AE Arrow Diagramming Method
AF Actual Finish Date
AOA Activity On Arrow
AON Activity On Node
AS Actual Start Date
BAC Budget At Completion
BCWP Budgeted Cost of Work Performed
BCWS Budgeted Cost of Work Scheduled
BOM Bill Of Materials
CA Control Account
CAP Control Account Plan
CCB Change Control Board
COQ Cost of Quality
CPAF Cost Plus Award Fee
CPF Cost Plus Fee
CPFF Cost Plus Fixed Fee
CPI Cost Performance Index
CPIF Cost Plus Incentive Fee
CPM Critical Path Method
CPPC Cost Plus Percentage of Cost
CV Cost Variance
CWBS Contract Work Breakdown Structure
DD Data Date
DU Duration
EAC Estimate at Completion
EF Early Finish Date
EMV Expected Monetary Value
ES Early Start Date
ETC Estimate to Complete
EV Earned Value
EVM Earned Value Management
EVT Earned Value Technique
FF Finish To Finish
FF Free Float
FFP Firm Fixed Price
FMEA Failure Mode and Effect Analysis
FPEFA Fixed Price with Economic Price Adjustment
FPIF Fixed Price Incentive Fee
FS Finish to Start
IFB Invitation For Bid
LF Late Finish Date
LOE Level of Effort
LS Late Start Date
OBS Organizational Breakdown Structure
OD Original Duration
PC Percent Complete
PCT Percent Complete
PDM Precedence Diagramming Method
PFD Planned Finish Date
PM Project Management
PM Program Management
PMBOK Project Management Body of Knowledge
PMIS Project Management Information System
PMO Program Management Office
PMO Project Management Office
PMP Project Management Professional
PS Planned Start Date
PSWBS Project Summary Work Breakdown Structure
PV Planned Value
QA Quality Assurance
QC Quality Control
RACI Responsibile, Accountable, Consult, and Inform
RAM Responsibility Assignment Matrix
RBS Resource Breakdown Structure
RBS Risk Breakdown Structure
RD Remaining Duration
RFI Request for Information
RFP Request for Proposal
RFQ Request for Quotation
SF Scheduled Finish Date
SF Start to Finish
SOW Statement of Work
SPI Schedule Performance Index
SS Scheduled Start Date
SS Start to Start
SV Schedule Variance
SWOT Strengths, Weaknesses, Opportunities and Threats
TC Target Completion date
TF Target Finish Date
TF Total Float
T&M Time and Material
TQM Total Quality Management
TS Target Start Date
VE Value Engineering
WBS Work Breakdown Structure
  [ Return To Top ]
 
For more information, see:
 
Free 30 Day Trial PMP Certification Practice Exams
Learn Why TestTaker PMP Certification Practice Exams Are A Great Deal.
 
 
About the PMP Exam Details Things to Know How to Prepare Resources
What Is PMP PMP Certification Exam PMP Knowledge Areas 60 Day PMP Study Plan PMP Practice Questions
What Is PMBOK How to Apply for the PMP PMP Processes 30 Day PMP Study Plan PMP Mock Exams
PMP Credential PMP Exam Registration PMP Formulas 2 Week Study Plan PMI.org
PMP Handbook PMP Exam Eligibility PMP Acronyms 1 Week Study Plan  
  PMP Exam Blueprint   PMP Test Taking Tips  
      What To Do if You Fail the PMP  
 
©Dantech Corporation, Inc. Privacy Policy Terms of Use
 
www.PMP-Certification-Exam.com and TestTaker are not affiliated with or endorsed by either Prometric or PMI in any way. The Prometric and PMI logos displayed here are for user reference and site content recognition as this site pertains to exam preparation materials for the PMP Certification Exam which is a proctored exam offered by Prometric. The Prometric logo and company name are trademarks of Prometric Inc. The PMI logo and company name are trademarks of the Project Management Institute.

With TestTaker, you will pass your PMP certification exam and you will be PMP certified. Register now for access to TestTaker's PMP Certification exam content. That's simulated PMP certification exams, PMP practice exams, and PMP practice questions.