PMP Formula: Estimate To Complete

PMP Formula Estimate To Complete

Estimate to Complete (ETC) is the expected cost to finish all the remaining project work. Estimate to complete (ETC) is a forecast of how much more money will need to be spent to complete the project. ETC can either be determined by building a bottom-up estimate, usually by asking your work package owners, team members, or vendors for revised estimates or by deducting the actual costs from the estimate at completion (EAC).

Formula Definition
ETC Estimate To Complete
= EAC - AC